CompTIA E2C Project Certification Exam

Question No: 231 – (Topic 3)

Which of the following is the primary purpose of a project tollgate?

  1. Review the tasks from the next phase of the project.

  2. Review changes to a project.

  3. Get acceptance to move the project to the next phase of work.

  4. Give a status update on a set of deliverables.

Answer: C

Question No: 232 – (Topic 3)

A project manager learns that a team member has falsified work experience, and does not have the knowledge required to complete the task. Which of the following should the project manager do?

  1. Reassign the individual to another role on the project team.

  2. Ignore the situation hoping that everything works out for the best.

  3. Assign other individuals to assist on the task to ensure the task does not get delayed further.

  4. Replace the member and ask the team manager to assign a more qualified person.

Answer: D

Question No: 233 – (Topic 3)

Which of the following is a tool that can be used to identify project team members that are responsible for a task or deliverable?

  1. Project charter

  2. Work Breakdown Structure (WBS)

  3. Project schedule

  4. RACI chart

Answer: D

Question No: 234 – (Topic 3)

All of the following are taken into account when determining the critical path EXCEPT:

  1. Late start and finish dates.

  2. Activity durations.

  3. Early start and finish dates.

  4. Resource limitations.

Answer: D

Question No: 235 CORRECT TEXT – (Topic 3)

Which of the following techniques could a project manager use to determine a project schedule based upon a variety of simulations?

Answer: Schedule network analysis

Answer: Critical chain method

Answer: Critical path method Answer: Monte Carlo analysis Answer: D

Question No: 236 – (Topic 3)

Which of the following steps should a project manager take to ensure the quality of project deliverables for a customer? (Select Two).

  1. The project manager should consult the project sponsor and customer to review the current quality requirements.

  2. The project manager should request a peer review of the project to determine if it meets the customers quality standards.

  3. The project manager should change the scope of the project to meet the customers expectations of quality standards.

  4. The project manager should check the finished product to determine if it meets the customers quality standards.

  5. The project manager should outsource to obtain the best resources for the project.

Answer: B,D

Question No: 237 – (Topic 3)

During which of the following process groups is the availability of required resources for the project determined?

  1. Executing

  2. Monitoring/Controlling

  3. Initiating

  4. Planning

Answer: D

Question No: 238 – (Topic 3)

A project manager was asked to complete a project three weeks early and not crash the project. Which of the following should be done?

  1. Move some of the task to another release.

  2. Have the team work over time and give them time off later to save the budget.

  3. Continue to work and complete the project as soon as possible.

  4. Review the plan with the team and develop a way to reduce the time

Answer: D

Question No: 239 – (Topic 3)

Which of the following would require that the project risk register be updated?

  1. A qualitative risk analysis is performed

  2. A stakeholder has concerns about material delays

  3. The risk management plan is created

  4. Increased costs for required materials

Answer: A

Question No: 240 – (Topic 3)

A project sponsor has requested that the training be delivered in parallel to a project#39;s implementation in order to ensure the project is delivered on schedule. If accepted, this request is an example of:

  1. the critical path method.

  2. crashing.

  3. fast-tracking.

  4. rolling wave planning.

Answer: C

100% Dumps4cert Free Download!
Download Free Demo:JK0-017 Demo PDF
100% Dumps4cert Pass Guaranteed!
JK0-017 Dumps

Dumps4cert ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No