Question No: 81 – (Topic 1)
A project has been running for four months. The planned value to this point is $100,000. The actual cost is an average of $30,000 per month. Earned value is $90,000. Which of the
following is the current cost performance index?
A. 0.75
B. 1.25
-
$20,000 over budget
-
Not enough detail to determine
Answer: A
Question No: 82 – (Topic 1)
A team member approaches the project manager and is concerned that the project is running behind and is overspending. Which of the following tools would the project manager use to validate the team member’s concern? (Select TWO).
-
CPI
-
AC
-
EV
-
PV
-
SV
-
BAC
Answer: A,E
Question No: 83 – (Topic 1)
Determining how to communicate general project information with a globally dispersed team has created scheduling challenges. Which of the following would BEST remedy the situation?
-
Provide a written forum that allows for asynchronous participation
-
Conduct a meeting at a time where everyone is inconvenienced
-
Schedule a meeting when the majority of the team is available
-
Establish a conference call with all team members
Answer: A
Question No: 84 – (Topic 1)
Once a project manager has been assigned, which of the following would the project manager do NEXT?
-
Develop task assignments
-
Finalize the project charter
-
Draft a communications plan
-
Conduct risk analysis
Answer: B
Question No: 85 – (Topic 1)
A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the project ahead or behind schedule?
-
SPI = 0.89, ahead of schedule
-
SPI = 0.90, behind schedule
-
SPI = 1.11, behind schedule
-
SPI = 1.20, ahead of schedule
Answer: D
Question No: 86 – (Topic 1)
Which of the following components of the project charter is used to help determine the project’s communication needs?
-
Stakeholder identification
-
Project objectives
-
Problem statement
-
Key deliverables
Answer: A
Question No: 87 – (Topic 1)
Which of the following is a document used iteratively during a project to capture strengths and weaknesses?
-
Quality plan
-
Scope document
-
Lessons learned
-
Business impact analysis
Answer: C
Question No: 88 – (Topic 1)
When a project manager creates a communication plan, which of the following should be included? (Select TWO).
-
Project communication formats
-
Financials
-
Red, yellow, and green project status
-
Escalation path
-
Overview of the project
-
Risks and issues
Answer: A,D
Question No: 89 – (Topic 1)
The project is half way through the schedule and the steering committee has approved a change request to add additional functionality to the program. The project manager’s NEXT step is to:
-
crash the schedule.
-
do an impact analysis.
-
look for ways to save money.
-
update the project plan.
Answer: D
Question No: 90 – (Topic 1)
Which of the following is the project manager implementing when allocating additional resources to a set of tasks that are in the critical path and are slowing down the project completion?
-
Crashing
-
Optimizing
-
Controlling
-
Fast tracking
Answer: A
100% Dumps4cert Free Download!
–Download Free Demo:PK0-003 Demo PDF
100% Dumps4cert Pass Guaranteed!
–PK0-003 Dumps
Dumps4cert | ExamCollection | Testking | |
---|---|---|---|
Lowest Price Guarantee | Yes | No | No |
Up-to-Dated | Yes | No | No |
Real Questions | Yes | No | No |
Explanation | Yes | No | No |
PDF VCE | Yes | No | No |
Free VCE Simulator | Yes | No | No |
Instant Download | Yes | No | No |