Question No.111
What is retesting?
-
Running the same test again in the same circumstances to reproduce the problem.
-
A cursory run through a test pack to see if any new errors have been introduced.
-
Checking that the predetermined exit criteria for the test phase have been met.
-
Running a previously failed test against new software/data/documents to see if the problem is solved.
Correct Answer: D
Question No.112
Which of the following is correct? Debugging is:
-
Testing/checking whether the software performs correctly.
-
Checking that a previously reported defect has been corrected.
-
Identifying the cause of a defect, repairing the code and checking the fix is correct.
-
Checking that no unintended consequences have occurred as a result of a fix.
Correct Answer: C
Question No.113
When is testing complete?
-
When time and budget are exhausted.
-
When there is enough information for sponsors to make an informed decision about release.
-
When there are no remaining high priority defects outstanding.
-
When every data combination has been exercised successfully.
Correct Answer: B
Question No.114
Which list of levels of tester independence is in the correct order, starting with the most independent first?
-
Tests designed by the author; tests designed by another member of the development team; tests designed by someone from a different company.
-
Tests designed by someone from a different department within the company; tests designed by the author; tests designed by someone from a different company.
-
Tests designed by someone from a different company; tests designed by someone from a different department within the company; tests designed by another member of the development team.
-
Tests designed by someone from a different department within the company; tests designed by someone from a different company; tests designed by the author.
Correct Answer: C
Question No.115
Which of the following is in the correct order (typically)?
-
Unit testing, system testing, acceptance testing, maintenance testing.
-
System testing, unit testing, acceptance testing, maintenance testing.
-
Acceptance testing, system testing, maintenance testing, unit testing.
-
Unit testing, maintenance testing, system testing, acceptance testing.
Correct Answer: A
Question No.116
Which TWO of the review types below are the BEST fitted (most adequate) options to choose for reviewing safety critical components in a software project?
-
Informal review.
-
Management review.
-
Inspection.
-
Walkthrough
-
Technical Review
Correct Answer: CE
Question No.117
Incidents would not be raised against
-
Requirements
-
Documentation
-
Test cases
-
Improvements suggested by users
Correct Answer: D
Question No.118
The cost of fixing a fault:
-
Is not important
-
Increases as we move the product towards live use
-
Decreases as we move the product towards live use
-
Is more expensive if found in requirements than functional design
-
Can never be determined
Correct Answer: B
Question No.119
Which of the following statements are TRUE?
-
Regression testing and acceptance testing are the same.
-
Regression tests show if all defects have been resolved.
-
Regression tests are typically well-suited for test automation.
-
Regression tests are performed to find out if code changes have introduced or uncovered defects.
-
Regression tests should be performed in integration testing.
-
A, C and D and E are true; B is false.
-
A, C and E are true; B and D are false.
-
C and D are true; A, B and E are false.
-
B and E are true; A, C and D are false.
Correct Answer: C
Question No.120
Which is not the fundamental test process?
-
Planning and control
-
Test closure activities
-
Analysis and design
-
None
Correct Answer: D