Question No.61
In an Agile approach, project values are most effectively implemented when they are determined by the:
-
sponsor
-
team
-
project manager
-
methodology
Correct Answer: B
Question No.62
According to the fundamental principles of Lean Management, errors result from:
-
Inadequate user requirements and documentation.
-
Misjudgment made by project teams and operations staff.
-
Flaws in development and production systems.
-
Insufficient management oversight of projects and operations.
Correct Answer: C
Question No.63
In Agile projects, the technique in which planning is done at three distinct horizons is known as:
-
Monte Carlo Analysis.
-
Portfolio Management.
-
DelphiTechnique.
-
Progressive Elaboration.
Correct Answer: D
Question No.64
Which of the following techniques best encourages osmotic communication?
-
Reviewing requirements frequently with the Product Owner
-
Having the Product Owner attend daily standups
-
Inviting the customer to attend every iteration demo
-
Seating the team members together in a work area
Correct Answer: D
Question No.65
The three questions asked atevery Daily Scrum should be: quot;What have you accomplished since the last Daily Scrum?quot;;quot;What are you planning to accomplish between now and the next Daily Scrum?quot;;and:
-
What is preventing you from completing your work effectively?
-
What is yourcurrent performance velocity?
-
Are you on track to complete assigned story points?
-
How many story pointswill you complete this sprint?
Correct Answer: A
Question No.66
The advantage of face-to-face collaboration emphasized in eXtreme Programming (XP) is that it:
-
allows team members to use common language in their design and code.
-
delays feedback much more than scheduled inspections.
-
eliminates communication delays and misunderstandings.
-
allows team members to correct some mistakes on the fly.
Correct Answer: C
Question No.67
What is the role in an eXtreme Programming (XP) project that ensures the right project processes are applied?
-
Domain Expert
-
Product Owner
-
ScrumMaster
-
Coach
Correct Answer: D
Question No.68
Which of the seven principles of software development is best intended to solve the problem of inventories causing hidden errors in the process?
-
Fast-Flexible-Flow
-
Optimize the Whole
-
Deliver Early and Often
-
Eliminate Waste
Correct Answer: D
Question No.69
Who is responsible for determining the business value of each feature?
-
Product Owner
-
Steering committee
-
ScrumMaster
-
Team
Correct Answer: A
Question No.70
Which layer of the product planning structure defines details at the capability or feature level?
-
Iteration
-
Roadmap
-
Release
-
Wave
Correct Answer: C